Zmiana jednostek projektu
Problem
Projekt utworzony w jednostkach Imperial, potrzebna zmiana na metric.
Rozwiązanie
To solve this challenge you have to open the piping.dcf (SQLite project) respectively <prefix<Piping-database (SQL Server). For SQLite-projects you can use for example SQLite Expert Personal to open the piping.dcf. Switch to the table PnPProject and look for the column Project_Standard. Here you can change the units of the Plant project:
- eImperial: for a British project
- eMetric: for a Metric project
- eMixedMetric for a Mixed-Metric project
Afterwards you have to re-open the project. If you select the project in the project manager you will note the units of the project